Rehabilitation process slide shows
Click the thumbnail images to learn more about the progress of the HP garage property reconstruction.
Each image links to a different slide show.
August 16
Another week of change rolls along as the shed gets cedar shingles and the house's second floor gets windows and custom rafter tail supports.
August 12
Progress in the house continues, along with preparations that will lead to a new, more accessible mounting for the landmark plaque.
August 9
Work on the house includes the fireplace and front dormer. Meanwhile a trench reveals a mystery.
July 28
The shed and garage get paper roofs, the fireplace gets a foundation, plumbing and heating systems go in, and more.
July 14
The house gets a new porch cover, electrical and plumbing, and the garage gets some weather proofing.
July 7
Reconstruction of the front porch begins. The porch area will return to its original open structure as it was in 1938.
June 30
The house window casings are reinstalled, framing completed on the back porch area, and the garage has its outer boards reattached.
June 21
From the ground up, every building receives the respectful treatment it deserves, including an all important treatment for termites.
June 14
The garage's new concrete curb has been poured, and the teardown of an old barn nearby provides a batch of wood perfect for garage repairs.